James Jernigan - Solar Energy Consultant

I don't sell solar. Solar sells itself. 

My job is to help interested homeowners get qualified, design the most efficient system possible, and save local families tens of thousands of dollars on their electricity bills.

Here's exactly what you can expect to happen once you've decided to go solar:

Wondering exactly how long it takes to go solar? You've signed the contract (or are close!), and now you need to know the real timeline from start to finish. It's a common question, and the answer is important for planning.

You should know that the "solar installation timeline" isn't just the few days installers are on your roof. It includes important planning and approval steps before and after the panels go up. While it varies, most home solar projects take 1 to 4 months from the day you sign the contract until your system is officially approved to operate (we call this PTO, or Permission to Operate). Why such a range? Let's break it down.

This guide will walk you through each phase, how long things usually take, and what might speed up or slow down your specific solar installation timeline.

Key Factors Influencing Your Solar Installation Timeline

So, why isn't there one simple answer to "how long does solar installation take?" It's because several players are involved, and some things take longer than others depending on where you live. Here’s what makes the biggest difference:

Your Local Permit Office: Getting the thumbs-up from your city or county building department is essential. Some offices work faster than others, and their backlog can affect your wait time. This is often the biggest variable.

Your Utility Company: Before you can flip the switch and start saving, your electric company needs to approve connecting your system to the grid. Their process and how busy they are play a huge role. This is the other big variable.

Homeowners Association (HOA): If you have an HOA, you'll likely need their approval too. Their meeting schedules and review process add another step.

Your Installer's Schedule & Know-How: How busy the installation crews are and how well the company manages the paperwork makes a difference. An experienced team can navigate the process more smoothly.

Equipment Availability: Sometimes, specific solar panels or parts might be on backorder, though this is less common now.

Weather: Heavy rain or high winds can sometimes delay the actual installation days for safety reasons. Your Help: Getting needed documents back quickly or providing easy access to your property helps keep things moving!

The Solar Installation Timeline: A Detailed Step-by-Step Breakdown

Let's walk through the whole process, from signing on the dotted line to powering your home with the sun.

Phase 1: Pre-Installation – Planning, Design & Approvals (The Longest Phase)

This part takes the most time and patience, but it’s where all the important planning happens to make sure your system is perfect for your home and meets all the rules.



Step 1: Consultation, Site Assessment & Final Proposa
l (Timeline: 1-7 Days Post-Contract)

What happens: We’ll schedule a visit (if needed after the initial consult) to take detailed measurements of your roof, check its condition, and look at your electrical panel. Your role: Confirm your final design choices and make sure our team can access the areas they need to check.

Step 2: System Design & Engineering (Timeline: 1-2 Weeks)

What happens: Our engineers get to work creating the detailed blueprints for your solar panel system. This includes precise panel placement, wiring plans, and making sure everything meets safety codes and structural requirements. Output: We create the official plans needed to apply for permits.

Step 3: Permitting (Local & HOA) (Timeline: 2 Weeks - 2+ Months)

What happens: This is often the longest waiting period. We submit the finished plans to your local city or county building department for their review and approval. If you have an HOA, we handle that submission too. How long this takes depends entirely on how busy their offices are and their specific process. Our Role: Our dedicated permitting team handles all the paperwork and follow-up to keep this moving as quickly as possible.


Step 4: Equipment Procurement (Timeline: Happens During Permitting)

What happens: While we wait for permits, we order the specific solar panels, inverters, and racking equipment needed for your approved design. This way, everything is ready to go once the permits are in hand.


Phase 2: Installation – Bringing Your System to Life (Surprisingly Fast!)

You might be surprised how quickly the physical installation happens once the planning and approvals are done!


Step 5: Physical Installation (Timeline: 1-3 Days)

What happens: Our professional crew arrives to get the job done!


Day 1: Usually involves preparing the roof and securely installing the racking system that holds the panels.

Day 2: Mounting the solar panels onto the racks and running the wiring.

Day 3: Installing the inverter (the box that converts solar power to usable electricity), making the final electrical connections, and cleaning up the site. Your role: Just ensure our crew has access to your roof and electrical panel area. We try to keep noise and disruption to a minimum.


Phase 3: Post-Installation – Inspection, Interconnection & Activation

The panels are up, but there are a few final, crucial steps before you can start generating your own clean energy and saving money.


Step 6: City/County Inspection (Timeline: 1-2 Weeks Post-Installation)

What happens: After the installation is complete, a local building inspector needs to visit. They'll check our work to make sure everything was installed correctly and meets safety codes. Scheduling this depends on the inspector's availability.


Step 7: Utility Interconnection Application & Approval (PTO) (Timeline: 2 Weeks - 2+ Months)

What happens: This is the second major waiting period. Once the system passes inspection, we submit the final paperwork, including proof of inspection, to your electric utility company. They review everything and give official "Permission to Operate" (PTO). This approval is required before your system can be legally connected to the grid and start sending excess power back (if you have net metering). How long this takes depends entirely on your utility company's process and workload. Important: You cannot turn your system on and start saving money until you receive official PTO from the utility.


Step 8: System Activation & Go-Live! (Timeline: Immediately after PTO)

What happens: Success! As soon as we get the green light (PTO) from your utility, we'll help you officially turn on your solar panel system. We’ll also walk you through how to use any monitoring apps so you can see your energy production in real-time. The Payoff: This is the moment you start generating your own clean power and watching your electricity bills go down!

Your Solar Installation Timeline at a Glance

Think of the process in three main stages: First, the pre-installation work including design and waiting for permits (this part takes the longest). Second, the actual installation on your home (usually just 1-3 days). Third, the post-installation steps like final inspection and waiting for utility approval (this can also take several weeks or more).


Going Solar Faster: How We Optimize Your Installation Timeline

While some parts of the solar installation timeline are out of anyone’s control (like permit office backlogs), choosing the right partner makes a big difference. Here’s how an experienced installer works hard to keep your project on track:

Experienced In-House Teams: Design and permitting specialists know the local rules and how to prepare paperwork correctly the first time, minimizing delays.

Strong Local Relationships: Working regularly with local permit offices and utility companies helps navigate their processes more efficiently.

Clear Communication: A dedicated project manager should keep you updated every step of the way, so you always know what’s happening.

Efficient Scheduling: Managing skilled installation crews effectively gets your system installed promptly once permits are approved.

Focus on Quality: Doing the job right the first time helps ensure your system passes inspection without needing corrections, saving valuable time.

Frequently Asked Questions (FAQ) About the Solar Timeline

Here are answers to some common questions about how long the solar process takes:

Q1: What's the absolute fastest a solar installation can happen? A: In a perfect world with quick permit and utility approvals, maybe around 4-6 weeks. But realistically, because of those outside factors, 1-4 months is a much more common timeframe from signing to activation (PTO).


Q2: What are the most common reasons for solar timeline delays? A: The two biggest factors are waiting for permit approval from your local government and waiting for interconnection approval (PTO) from your electric utility company. HOA review can also add time.


Q3: Do I need to be home during the entire installation process? A: Not necessarily for the whole time. You'll likely need to be there for the initial site assessment and possibly parts of the installation days (for access) and the final inspection. We work with your schedule as much as possible.


Q4: How soon after installation will I start saving money? A: You start saving money the moment your system receives Permission to Operate (PTO) from the utility company and is officially turned on – not immediately after the panels are installed.


Q5: How does weather impact the installation schedule? A: Heavy rain, snow, ice, or very high winds can delay the days our crews are physically working on your roof for safety. Usually, this only pushes the installation back by a day or two.


Q6: What if my HOA causes delays? A: We submit the necessary paperwork to your HOA according to their process. If there are delays, we follow up, but ultimately their review timeline is up to them. We help you provide any needed info.


Q7: Can I speed up the permitting or utility approval process? A: Unfortunately, homeowners usually can't directly speed up the government or utility company's review times. However, making sure all your information is accurate and responding quickly if we need anything from you helps us submit everything promptly and correctly, which avoids preventable delays on our end.


Taking the Next Step Towards Solar Savings

Now you have a clearer picture of the typical solar installation timeline. While it involves several steps and takes an average of 1-4 months, remember that the longest parts are often waiting for approvals. The actual on-site work is quick!

Choosing an experienced installer helps ensure the process is managed smoothly and efficiently. Once you get that Permission to Operate, you'll be enjoying lower energy bills, greater energy independence, and the satisfaction of using clean, renewable power for years to come.

Ready to find out what the timeline looks like for your home? Let's chat! Schedule a quick, free 15-minute consultation, and we'll give you a personalized estimate based on your location and home.

solar installation timeline

DID YOU KNOW

Many VA homeowners are able to go solar at NO COST!

New government programs and financing options make it possible for many homeowners to go solar without spending any money at all. That means no cash, no loan, and no upfront payment is required whatsoever to get panels installed on your home and start saving money.  In many cases, we can simply switch your current expensive and ever-growing utility bill for a much lower fixed monthly payment, locking in that lower rate for the next 25 years!

LEARN MORE

James Jernigan is an independent solar energy consultant.